In late April of this year, Millennium Tower's foundation was laid as Suffolk Construction crews executed the largest continuous concrete pour in Boston's history. Over the course of 22.5 hours, 572 concrete trucks funneled 6,000 cubic yards of concrete into the Downtown Crossing pit. As June begins, crews continue foundation work on the highly anticipated luxury residential building in Boston's midtown neighborhood.

https://youtu.be/ZLHDdtnY4lg

Once construction work in completed in 2016, Millennium Tower will rise over 600 feet above the heart of Boston, forever altering the city's skyline as well as its notion of luxury condominium living.

 

Millennium Tower Boston Foundation Work

Millennium Tower Boston Foundation Work

 

 

Millennium Tower Boston Site

Millennium Tower Boston Site